PERT Network Diagram Online
Online PERT network diagram tool. Calculate the critical path, project duration and slack time, with Gantt chart visualization.
What is PERT three-point estimation?
Expected time = (Optimistic + 4 × Most likely + Pessimistic) / 6. Three-point estimation reduces uncertainty and is well suited to estimating durations for innovative projects.